1废水池环氧胶泥防腐施工施工方案2008年二月2目录1
0编制原则及依据··········································································32
0施工准备·····················································································33
0施工方法·····················································································44
0质量保证·····················································································65
0产品防护措施·············································································86
0施工进度保证措施······································································831
0编制原则及依据1
1编制原则及依据1
1为业主编制科学合理的工程建设计划提供依据;1
2作好施工前的准备工作,为保证资源供应提供依据;1
3为确定低成本、高质量、快工期的施工可行性和经济合理性提供依据;1
4以工程的高质量、快工期、文明、安全、环保、经济、实用为中心思想编制本施工组织设计;1
5从公司的工程师和专家及在类似工程施工的老技术人员经验中学习,并参考了一部分实用的施工技术规范
6《涂装前表面处理规范》(SYJ4007-86)1