施工组织设计目录第一章、编制说明及依据········································1第二章、工程概况··············································3第三章、施工总平面布置及说明··································5第四章、施工准备··············································7第五章、施工部署·············································10第六章、各项保证措施·········································18第七章、施工技术方案·········································31第八章、工程重点、难点施工技术措施···························55第九章、成品保护措施·········································57第十章、质量承诺及保证措施···································60第十一章、安全文明施工措施···································79第十二章、工期承诺及保证措施·································99第一章、编制说明及依据一、编制说明:根据建设单位提供的施工图、招标文件、发标会、补遗书及答疑书解释,参考现行国家规范标准和昆明市建设工程管理条例及地方规范标准,结合我公司多年来的施工经验,针对本装修工程项目的施工重点和难点,本着保证质量;保证工期的最终要求,经我公司多次研究讨论和比较
最终提出了我公司的理解和建议,以及我公司中标后将如何组织施