茂名市水东湾碧桂园城市花园项目五期(二)工程外脚手架施工方案目录1.编制依据.............................................................................12.工程概况.............................................................................13.搭设方案.............................................................................23.1方案概况..........................................................................23.2脚手架构造........................................................................23.3材料要求..........................................................................33.5落地式双排脚手架..................................................................43.6进度计划..........................................................................44.搭设要求.............................................................................54.1搭设前准备工作....................................................................54.2搭设时注意事项....................................................................65.脚手架斜道与电梯井道及卸料平台.......................................................76.脚手架防电避雷措施、防火措施.........................................................96.1、防电避雷措施.....................................................................96.2、防火措施........................................................................107.脚手架的监测、验收和使用管理........................................................117.1脚手架的监测.....................................................................117.2脚手架的验收......................................................................137.3脚手架搭设的技术要求与检验方法...................................................147.4脚手架的使用管理规定.............................................................158.必须执行的强制性条文................................................................169.脚手架搭设与拆除安全技术措施........................................................179.1脚手架搭设.......................................................................179.2脚手架拆除.......................................................................1810.应急施工预案.......................................................................1910.1应急预案概况....................................................................1910.2安全管理及应急救援机构设置......................................................1910.3报警救援及其他联络电话..........................................................1910.4人员分工与职责..................................................................1910.5应急救援工作程序................................................................2010.6应急救援方法....................................................................2010.7预备应急救援工具................................................................2310.8应急救援启动条件及逃生路线......................................................2311.验算书(落地式及拉吊式脚手架).....................................................24验算:落地式双排扣件式单立杆钢管外脚手架的稳定性.....................................2412.附图...............................................................................32茂名市水东湾碧桂园城市花园项目五期(二)工程外脚手架施工方案1.编制依据1、本工程施工图纸及相关设计变更单;2、《建筑施工扣件式钢管脚手架安全技术...