目 录1、工程概况···············································································22、施工准备···············································································33、主要分部分项工程施工方法·····················································104、厂区设施施工·······································································315、施工总进度计划及措施···························································346、质量保证措施·······································································377、安全生产措施、环境保护、文明施工措施···································498、安全生产管理、费用及责任人员落实情况···································601、工程概况1.1 工程概况工程项目组成:1.2 施工技术难点及处理措施1、砼浇筑:体积小、断面小,易出质量问题。严格从半成材料开始控制,认真按工艺流程作业,从立模→拌合→运输→浇筑→捣实→收面→养护,每一道工序严格控制。2、集水池工程:部分施工用材料需采用人工二次转运,我单位将采用拓宽人行路面,尽可能采用小型拖拉机结合胶轮车运输。3、附属设施工程:本工程主要为水处理厂工程,还涉及办公楼入厂公路等,组成项目较多。本工程拟组织多个工程施工班组,精心安排施工组织,在施工中严格执行相关的规程规范,按设计要求进行施工。1.3 项目施工管理的重点1)、项目领导班子强抓各分项工程协调工作。本工程由项目经理直接协调各分项工程施工班组施工进度,保证工程按时实施。2)、我单位保证拟派前往该项目工程实施管理人员,施工队伍都是具有类似工程丰富施工经验。并且对该项目工程实施中资金保证。3)、文明施工,尊重当地民风民俗。4)、由于本工程时间紧、任务重、施工场地有限...