下载后可任意编辑PMP 模拟题 1 项目管理师 (上海套题 1)声明:以下试题与 PMP 考试的类型相同。本试题仅为检验复习成效。1. Effective stakeholder management includes all of the following project elements except:A. Clear requirements definitionB. Scope change controlC. Timely status informationD. Frequent cost reports有效的项目干系人治理包括以下所有的项目元素,除了:A. 清楚的需求定义B. 范畴变更操纵C. 及时的状态信息D. 常常的成本报告2. A project is:A.A process of considerable scope that implements a planB.A group of ideas managed in a coordinated way to obtain a desired outcomeC.A temporary endeavor undertaken to create a unique product or serviceD.A series of tasks or functions that must be completed by a certain date项目是:A.一个实施一个打算的相应范畴的过程B.一组以协作方式治理、获得一个期望的结果的主意C.创立专门的产品或服务所承担的临时努力D.一系列必须在一个确定日期完成的任务或功能3. Which of the following is not a characteristic of project phase?A. MilestonesB. ObjectivesC. EstimatesD. Deliverables以下哪一项不是项目时期的一个特性?A.里程碑B.目标C.估量D.项目可交付成果4. In which type of organization, the project manager’s role most likely part-time?A. FunctionalB. ProjectizedC. Weak MatrixD. Strong Matrix下载后可任意编辑在哪一种类型的组织中,项目经理的角色更像是兼职的?A.职能型B.项目型C.弱矩阵型D.强矩阵型5. The greatest degree of uncertainty is encountered during which phase of the project life cycle?A. ConceptB. PlanningC. ImplementationD. Closeout在项目生命周期的哪一时期会遇到最大程度的不确定性?A.概念B.打算C.实施D.收尾6. The disorientation experienced by people who suddenly find themselves living and working in a different environment is known as:A. Culture shockB. Socio-centrismC. Temporal shockD. Ethno-centrism突然发觉自己生活工作在一个不同环境中的人所经历的不知所措的感受被称为:A. 文化冲击B. 社会优越感C. 临...