】郑州华电高科电力设备工程有限公司江苏盐城射阳港电厂 3#
4#机组电除尘拆除施工方案编制: 审核: 第 2 页 共 14 页下载后可任意编辑审批: 编制单位:山东军辉建设安装工程有限公司2024 年 10 月目录1
工程概况··········································32
编制依据··········································33
作业前应具备的条件································34
主要施工机具····································· 45
组织机构及劳动力配置····························· 46
施工工期········································· 57
拆除的顺序及方法································· 58
安全措施········································· 69
危险点(源)····································· 1010
施工环境保护·································1211
施工进度计划·································12第 3 页 共 14 页下载后可任意编辑一、工程概况江苏盐城射阳港发电厂 3#4#机组除尘器为电气除尘器,3#4#机组各对应一台除尘器,每台除尘器分为六个电场,大致设备有:除尘器支架、除尘器壳体阴极板、阳极板、灰斗、冲灰器、阳极板振打器、阴极板