总工程量合同单价/预算单价一、合同内1A7-1系统㎡1832.39龙骨安装㎡1832.39防火保温安装㎡1832.39面材安装㎡1832.39打胶清理㎡1832.392A7-2系统㎡964.52龙骨安装㎡964.52防火保温安装㎡964.52面材安装㎡964.52打胶清理㎡964.523A8系统㎡4623.48龙骨安装㎡4623.48防火保温安装㎡4623.48面材安装㎡4623.48打胶清理㎡4623.484A9系统㎡2601.52龙骨安装㎡2601.52防火保温安装㎡2601.52面材安装㎡2601.52打胶清理㎡2601.525A10系统㎡1123.64龙骨安装㎡1123.64防火保温安装㎡1123.64面材安装㎡1123.64打胶清理㎡1123.646A11系统㎡231.19龙骨安装㎡231.19防火保温安装㎡231.19五金爪件安装㎡231.19面材安装㎡231.19打胶清理㎡231.195A12系统㎡248.59龙骨安装㎡248.59清单编号分项工程名称单位合同总额防火保温安装 ㎡248.59面材安装㎡248.59打胶清理㎡248.595A13系统㎡856.15龙骨安装㎡856.15防火保温安装㎡856.15面材安装㎡856.15打胶清理㎡856.155B3系统㎡266.89龙骨安装㎡266.89防火保温安装㎡266.89面材安装㎡266.89打胶清理㎡266.895C3系统㎡23638.45龙骨安装㎡23638.45防火保温安装㎡23638.45面材安装㎡23638.45打胶清理㎡23638.455C4系统㎡1317.69龙骨安装㎡1317.69防火保温安装㎡1317.69面材安装㎡1317.69打胶清理㎡1317.695D1系统㎡4189.12龙骨安装㎡4189.12防火保温安装㎡4189.12面材安装㎡4189.12打胶清理㎡4189.125D2系统㎡100.48龙骨安装㎡100.48防火保温安装㎡100.48面材安装㎡100.48打胶清理㎡100.485E系统㎡861.40龙骨安装㎡861.40防火保温安装㎡861.40面材安装㎡861.40打胶清理㎡861.405F系统㎡2748.27龙骨安装㎡2748.27防火保温安装㎡2748.27面材安装㎡2748.27打胶清理㎡2748.275G系统㎡1308.65龙骨安装㎡1308.65防火保温安装㎡1308.65面材安装㎡1308.65打胶清理㎡1308.656旋转门2.007预埋件9.00措施费1.00样品项1.00材料的安全保管项1.00材料的运输项1.00在施工过程中清除垃圾项1.00场外制作项1.00定线放样项1.00防火项1.00清理及移交项1.00工程验收项1.00保险项1.00施工机械项1.00脚手架与临时支撑项1.00临时照明、供电和采暖 项1.00样板费用及成品保护 项1.00四性实验费用 项1.00配合费用 项1.00安全文明措施项1.00临时设施项1.00系统检测费项1.00材料检测费项1.00成品保护 项1.00清洁费项1.00外来人员保险费项1.00深化设计费用 项1.00验收检验费项1.00竣工图项1.00埋件复合补埋项1.00防雷项1.00视觉样板项1.00二次开洞及封堵...