号隧道线施工写实表值班人员:日期:()至日期:(次日)掌子面里程工序名称人数时间段落所用时间所用机械、材料现场施工情况说明:主要描述在施工过程中人员数量、机械完好率、班组工序衔接等是否的问题,并提出改进措施。开始时 间结束时 间上台阶开挖( m)定位打眼凿岩台车台装药、放炮通风出渣自卸车:台、测量,地质素描初喷罐车:台、湿喷台车台、支护类型 ___ 上台阶支护___榀 ___(m) 下台阶支护___榀 ___(m) ___ 挂第一层钢筋网片及立架锚杆根,移动平台车台破锤台挂第二层钢筋网片复喷第二层砼罐车:台、湿喷台车台、两个循环打锚杆及注浆砼方,注浆机台现场工程师:日期: ___________ 生产副经理: ____________日期: _____________ Tunnel TUBE Construction Record On Duty: Date: () Until: (Next Date )Chainage Process name PEOple TIME SPEND Material and Mechine Site construction : Description: The main description of the number of personnel in the construction process, the integrity of the machine, the team process, such as the convergence of the problem, and propose improvements START END Top heading excavation (m)Drill borehole Tunnel drilling machine pc Charge and Blasting Ventilation Mucking Dump truck:pc Face mapping and Geodetic checking of profile Initial shotcrete Concrete mixer:、Shotcrete machine pc Category___ TOP heading primary support ___榀___(m) Bench primary suppor ___榀___(m) ___ Wire mesh and Lattice girder Anchor pc,Mobile platform pc. Tunnel excavator pc Second Wire mesh Shotcrete Concrete mixe :pc 、Shotcrete machine pc、Anchor ahd Grouting After Two rounds Concrete quanity ,Injection machine pc 台Site Engineer: Date: ___________ Production Deputy Manager: ____________ Date: _____________ Zapisnik o konstrukciji tunelske cijevi Na du?nosti: Datum: ()Do: (Slede?i datum) Staciona?aIme aktivnosti Radna snaga VRIJEME POTRO?ENO Materijal i m a?ineGradili?te: Opis: Glavni opis broja osoblja u proce...