矿业集团望峰岗井-817m北翼C15顶板运输大巷掘进作业规程目录第一章概况第一节概述...................................................2第二节编写依据................................................2第二章地质水文情况.............................................2第一节地质构造................................................2第二节水文地质................................................2第三章巷道布置及支护说明..........................................2第一节巷道布置................................................2第二节支护设计................................................3第三节支护工艺................................................6第四章施工工..................................................7第一节施工方法................................................7第二节凿岩方式...............................................8第三节爆破作业................................................8第四节装、运岩方..............................................8第五节管线及轨道敷设............................................8第六节设备及工具配备..........................................9第五章劳动组织及主要技术经济指标....................................9第一节劳动组织...............................................9第二节主要技术经济指标.........................................10第三节循环作业图表............................................11第六章主要生产系统............................................11第一节通风系统................................................11第二节压风、防尘、防灭火系统.....................................12第三节通讯系统................................................12第四节排水系统...............................................13第五节供电系统................................................13第六节安全监测系统...........................................13第七章灾害预防及避灾路线........................................14第八章安全技术措施..............................................16第一节施工准备................................................16第二节“一通三防”管理.........................................16第三节顶板管理...............................................18第四节爆破管理................................................18第五节防治水管理..............................................22第六节机电管理................................................23第七节平巷运输管理............................................25第八节扒矸机使用管理规定........................................25第九节电瓶车运输措施............................................27第十节锚杆拉拔力测试安全技术措施...................................27第十一节预防煤与瓦斯突出管理规定.................................29第九章其他...............................................29第十章附图.................................................301.煤岩层综合柱状图2.巷道布置平面图3.爆破警戒示意图4.通风系统示意图5.压风、防尘、防灭火系统示意图6.排水系统示意图7.监测、监控、断电示意图8.避灾路线示意图第一章概况第一节概述一、巷道名称本作业规程掘进的巷道为-817m北翼C15顶板运输大巷。二、掘进目的及巷道用途掘进目的是为了形成北翼采区的运输生产系统,满足该采区煤层回采的运输、通风及管线敷设的需要。三、巷道设计长度及服务年限巷道设计长度及坡度:1、巷道设计总长度:2054m;2、坡度:从三号交岔点向北按3‰坡度施工。四、预计开工时间:2007年6月14日。五、预计竣工时间:2009年6月30日。第二节编写依据一、《煤矿安全规程》及局、矿有关安全...