Method and technical measure of electrical w orks 电气主要施工方法和技术措施: A
Process 施工工艺: Conduiting → cabling → installation of lighting fixtures, switches, sockets → power on and commisioning 配管 → 配线 → 安装灯具、开关、插座 → 送电调试 B
Construction notice 施工要点: Surface PVC conduit and pipe in ceiling and recessed PVC conduit and pipe in floor along walls will be provided to the project
Conduiting, which serves to civil works, HVAC and water supply and drainage, should be arranged according to drawings and can not be changed freely
Construction should comply to process standard of national acceptance regulation
本工程管线敷设为吊顶内明敷设 PVC管及电管和沿墙地坪内暗配PVC管和电管
配管必须与土建、暖通和给排水专业密切配合,按图施工,不得随意变动,施工中必须按照国家验收规范有关工艺标准施工
Surface conduit and recessed conduit will be adopted in the project
Conduits should be connected