青岛润亿清洁能源有限公司综合利用工程TRT 透平机出口煤气管道膨胀节更换施工作业指导书编制:审核:批准:西安陕鼓动力股份有限公司二零一六年七月施工组织设计/方案审批表 工程名称TRT 透平机出口煤气管道膨胀节更换编制人部 门审 批 意 见责 任 人施工单位项目经理部审批技术部门负责人:年 月 日质量部门负责人:年 月 日安全部门负责人:年 月 日项目负责人:年 月 日总包单位技术部门负责人:年 月 日项目经理部审批质量部门负责人:年 月 日安全部门负责人:年 月 日总工程师:年 月 日目录一、适用范围···················································1二、编制依据 ··················································· 3 三、施工慨况 ······················································1 四、施工人力资源安排 ··········································· Error: Reference source not found五、主要施工工器具 ··········································· Error: Reference source not found 六、施工组织体系 ···············································2 七、施工方法 ··················································4 八、施工质量技术保证措施 ···································6 九、施工安全保证措施 ···········································6 十、 危险源辩识与风险评价及控制对策 表 ······························· 7 一、适用范围为了提高煤气管道更换膨胀节的施工安全加强安装工艺和质量,特制定本方案。本施工方案适用于青岛润亿清洁能源有限公司综合利用工程 1#、2#TRT 透平机出口煤气管道膨胀节更换。二、编制依据1。1 编制原则1)积极响应招标文件的规定,确保工期、质量、安全目标的实现;2)在总体部署和资源配置上尽量做到科学、优化...