淬火炉安全操作规程Safe operation rules for quenching furnace一、开机前的准备Preparations before starting up1
关闭各控制柜门并检查门碰开关可靠有效;Close all control cabinet and check whether door touch switch is reliable and effective;2
检查控制面板指示灯完好;检查各接地线可靠连接
Check whether indicator light of control panel is in good condition; Check whether grounding wire is reliably connected
二、开机作业Starting up operation① 将热电偶引线“+ —"接于仪表后部接线端
Connect the lead of thermocouple“+ —”with terminal located in the rear part of gauge
② 将电进线和输出线按接线图所示,接于控制器接线板上
Connect input line and output line with the wiring board of controller according to wiring diagram
③ 调节调零器使指针位于“0”位
Adjust zero adjuster to make pointer stay“0”position
④ 打开电源开关,将温设定调至所需温度
Turn on the power switch , and adjust the temperature to the desired temperature
⑤ 打开温度控制器电源开关,绿灯亮,接触器吸合