二采区水泵房设备安装施工组织设计矿 长: 总 工: 安全矿长: 机电矿长: 安全副总: 机电副总: 安全管理部:通风灭火部: 机电运输部:审 核: 编 制:马幼君二零一七年十一月目 录一、工程概况 ··································2 (一)、水泵主要 ································2(二)、电控主要设备 ····························2二、组织措施 ··································3三、施工工期 ··································4四、主要设备明细 ·······························4五、施工步骤 ··································5(一)、电控系统 ································5(二)、泵体、电机及管路························5(三)、辅助设施安装 ····························6(四)、上位机系统 ······························6(五)、收尾工作 ································6六、调试试车 ···································6七、主要安全技术措施 ···························7八、主要风险管控措施 ···························7附图一:泵房设备布置意识图附图二:水泵基础图一、工程概况根据矿生产继续计划安排,井下二采区需安装加压水泵 3台,为使此项工作安全顺利进行,特制定如下施工方案及安全技术措施,请相关区队及所