笑嘻嘻大厦物业接管验收手册项目名称:进展大厦文件编号版本号发布日期编 制校 对审 核批 准 目 录接管验收小组·································2物业设施设备接管工作流程图·······················3物业移交资料参考表·······························4楼层公共部位验收表·······························9室外公共设施验收表·······························9消防系统验收表···································11电梯(直梯)系统验收表····························12供配电系统验收表·································14安防系统验收表···································16二次供水系统验收表·······························17中央空调系统验收表·······························18设施设备验收问题记录表···························20物业设施设备移交清单·····························21物业资料移交清单·································22接管验收小组组 长:副组长:下设两个分小组:1、文件资料接管小组 责任人:职责:负责接管项目的工程图纸、设备相关资料的移交工作;业 户资料的移交以及协助楼宇的验收移交工作;2、现场验收接管小组 责任部门: 责任人: 职责:负责项目房屋主体、公共设施和机电设备的验收交接和钥匙接管工作
物业设施设备接管工作流程图 相关技术人员提出、明确接管验