山 西 高 硫 煤 洁 净 利 用 化电 热 一 体 化 示 项 目 主 体 工 程 安 装 1标段2×240t/h 循环流化床锅炉安装方案河 南 省 安 装 集 团 XX 公 司二 ○ 一 五 年 四 月目 录第一章 概述······································1第 二 章锅炉钢架组合吊装··························4第 三 章空气预热器安装····························9第 四 章水冷壁安装································11第 五 章省煤器安装································13第 六 章过热器安装································14第 七 章锅筒与下降管······························15第 八 章旋风分离器安装····························16第 九 章汽水连接管与其它管道安装 ··················17第 十 章 锅炉水压试验·····························18第 十 一 章 锅炉化学清洗·····························22第 十 二 章 质量保证措施·····························26第 十 三 章 安全生产、文明施工措施 ···················30附1 劳动力安排···································34附2 主要施工机具安排·····························35附3 本工程需用规程、规、标准 ···················46附4 钢架排架拼装示意图···························47附5 塔吊布置位置示意图···························48一、工程概况山西高硫煤洁净利用化电热一体化示项目主体工程是由中机国能电力工程设计、总包施工的EPC 项目工程,该工程是年产100 万吨甲醇厂的供热装置,我公司专业分包该主体工程安装Ⅰ标段的施工任务,主要施工容为锅炉厂制造的2×240t/h 循环硫化床锅炉的安装。该锅炉型号:YG—240/9.8—M18、额定蒸发量:240t/h、额定蒸汽压力...