XX 二期拆迁安置还房项目4#~11#楼电动吊篮专项施工方案批准: 审核: 初审: 编制: XX 二期拆迁安置还房项目部2012 年 5 月 12 日目 录一.编制依据........................................................................1二.工程概况........................................................................1三.施工准备........................................................................13.1技术准备.......................................................................13.2吊篮验算.......................................................................33.3技术要求.......................................................................93.4生产准备......................................................................10四.吊篮安装施工方法...............................................................104.1安装流程......................................................................104.2安装方法......................................................................10五.安全管理措施...................................................................11六.成品保护.......................................................................12一.编制依据1.1工程施工图纸;1.2电动吊篮使用说明书;1.3高处作业吊篮安全规则(JGJ5027-1992)。二.工程概况本工程外墙保温、涂料施工,采纳电动吊篮施工。三.施工准备3.1技术准备3.1.1 吊篮选型及性能说明本工程外墙装修为涂料工程为外墙外保温,施工荷载较小(总计约200kg),拟选用DL630型高处作业吊篮(提升机提升力 400kg)。3.1.1.1 篮体篮体宽度 600mm,长度分别有 4 米、6 米、7 米。底篮及侧板用网纹钢板制作, 平台靠墙面有靠墙防撞装置,能防止工作表面受撞破损。吊篮四周设有高 1170mm 的护 栏,底部设有地轮,以利于在现场移动。吊篮上还装拉结用的锚固器,以便于吊篮较 长时有与建筑物间停置于一处,完成较复杂的装修作业,如图 3.1-1。吊篮篮体组装图3.1.1.2 提升机DL630 型吊篮采纳 α 型动力提升机(提升力 400kg),采纳低电流牵引,并有突 然停电情况下的手动升降装置。同时,该提升机采纳三相盘式制动异步电动机,其技 术性能完全符合吊篮操作中启动迅速,断电瞬时刹停以及起动...