房屋拆除(外立面)工程编制人: 审核人:编制日期:2025 年 5 月 24 日目 录一、编制依据
···············································2二、拆除工程的概况及特点····································2三、拆除建筑物实体(照片 ) ····································3四、拆除方案总体部署·········································6五、主要施工方法···········································8六、组织机构···············································10七、施工进度计划· ·········································13八、机具设备需用计划·······································14九、安全、消防、保卫、文明施工管理····························15十、防尘方案···············································19十一、应急预案··············································21十二、文明措施··············································30一、编制依据(1)甲方提供的相关图纸(2)北京市建筑物、构筑物拆除规程(DGJ08-70-2025)(3)建筑拆除工程安全技术法律规范(JGJ147-2025)(4)北京市建筑物构筑物拆除工程安全管理规定(5)北京市扬尘污染防治管理办法(6)市建委公