G3012阿克苏至喀什高速公路工程第AK-1合同段K1050+490小桥施工组织设计浙江省交通工程建设集团有限公司G3012阿克苏至喀什高速公路第AK-1标项目经理部二0一一年七月目录一、编制依据············································1二、编制原则············································1三、工程概况············································1四、施工准备及施工计划··································2五、详细施工方法和工作程序······························3六、施工质量控制措施····································10七、安全保证措施········································13八、施工技术、安全生产交底······························18九、环保措施············································18十、文明施工措施·······································21十一、消防安全措施·····································24十二、冬、夏季施工安排及防洪措施·······················25十三、廉政建设保证措施·································28十四、与业主、监理的配合措施···························29附件:施工技术、安全生产交底书K1050+490小桥施工组织设计一、编制依据1、《公路桥涵施工技术规范》(JTJ041-2000)2、《公路工程质量检验评定标准》(JTGF80/1-2004)3、《阿克苏至喀什高速公路工程施工招标文件》4、《阿克苏至喀什高速公路工程施工投标文件》5、《阿克苏至喀什高速公路工程两阶段施工图设计》(第一合标段)二、编制原则本工程按照“突出重点、统筹兼顾、科学组织、均衡生产”的原则进行编制,具体安排如下:1、据工程的实际情况,围绕重点工程项目,周密部署、合理安排、科学管理;2、采用多点平行流水作业及均衡施工方法,运用网络技术控制施工进度,保证施工工期的完成;3、严格遵循有关环保、水利、国土及其他相关部门(如南疆铁路)工作规定,采取切实可行的保护方案和保护措施,配合当地政府有关部门和水保部门做好环保和水保工作;4、合理配备生产要素,优化施工平面布置,减少工程消耗,降低生产成本;5、选派经验丰富、技术水平高的管理人员和技术人员组织强有力的现场管理机构,安排有同类和类似工程施工经验的专业施工队伍,按照业主要求组织专业化施工。三、工程概况K1050+490小桥作为我项目部小桥的首件工程,该小桥为1-8.0m,基础为轻型桥台,地基容许承载力不小于350KPa,小桥进口两侧接人字坝。主要材料:现浇混凝土板顶铺装采用C40混凝土;现浇行车道板、台帽、台身、扩大基础、墙身及基础采用C30混凝土。主要工程量见下表:铺装层上部构造搭接板现浇C40混凝土(m³)HRB335(kg)现浇30混凝土(m³)HPB235(kg)HRB335(kg)C30混凝土(m³)HRB335(Kg)20.542696.66.4482941510684.611840波形梁护栏(警示柱)挡块现浇30混凝土(m³)HPB235(kg)HRB335(kg)钢材(kg)现浇C30混凝土(m³)HPB235(kg)HRB335(kg)6.44137.2279.43920.3420118.6台帽台身台基现浇30混凝土(m³)HPB235(kg)HRB335(kg)2cm橡胶垫(m³)现浇C30混凝土(m³)钢筋(kg)现浇C30混凝土(m³)43.48118401553119697055.07台基耳墙支撑梁钢筋(kg)现浇C30混凝土(m³)砂砾垫层(m³)HPB235(kg)HRB335(kg)现浇C30砼钢筋(kg)10217.06718.67.44180288四、施工准备及施工计划项目部进场以来,对K1050+490小桥位置、交角、高程、孔径等作了详细的复核。小桥施工所需的机具、材...