新建沪昆客专贵州段CKGZTJ-9标段大独山高风险隧道专项施工组织设计编制:复核:审核:中铁二十局集团第二工程有限公司2010年11月24日目录第一章编制依据、编制范围及设计概况···················1第一节编制依据···························1第二节编制原则···························1第三节编制范围···························2第二章工程概况·····························3第一节技术标准···························3沪昆客专长昆贵州段极高风险隧道指导性施工组织设计第二节自然条件···························3第三节建设条件···························9第四节设计概况···························10第五节工程特点、重难点及主要风险··················17第三章总体施工组织安排·························19第一节建设管理目标·························19第二节施工管理机构与任务划分····················20第三节总体施工原则与顺序······················21第四章施工进度计划···························23第一节主要工效指标和技术要素····················23第二节分工作面施工进度安排·····················23第三节关键线路分析、关键工作面工期检算···············24第四节进度计划图表·························24第五节确定总工期和重要阶段工期·····