溪古水电站引水隧洞工程(合同编号:XG/CⅢ-2)目录【施工组织设计】第一章工程概况.............................................11.1工程概况.................................................................................................................11.2水文气象和工程地质............................................................................................21.3对外交通及场内交通条件....................................................................................51.4承包人承担的合同项目及工作内容....................................................................51.5发包人承担的工程项目和工作内容....................................................................71.6其它承包人承担的工程项目和工作内容............................................................71.7招标文件控制工期................................................................................................7第二章施工总体目标及施工组织机构...........................82.1施工目标.................................................................................................................82.2组织机构及职能....................................................................................................9第三章施工总布置..........................................123.1施工布置原则.......................................................................................................123.2场内交通布置.......................................................................................................133.3施工风水电、照明及通讯..................................................................................133.4混凝土拌和系统..................................................................................................163.5机械修配厂和设备停放场..................................................................................163.6综合加工厂..........................................................................................................173.7仓储系统..............................................................................................................173.8现场材料及工艺试验室......................................................................................183.9办公及生活营地..................................................................................................183.10碴场规划.............................................................................................................18第四章施工总进度............................................204.1编制依据及原则..................................................................................................204.2施工进度..............................................................................................................204.3关键线路..............................................................................................................214.4主要强度指标.......................................................................................................21-1-溪古水电站引水隧洞工程(合同编号:XG/CⅢ-2)【施工组织设计】4.5主要施工资源配置..............................................................................................21第五章石方洞挖工程........................................235.1概述.....................................................................................................................235...