第0页共73页编号:时间:2021年x月x日书山有路勤为径,学海无涯苦作舟页码:第0页共73页目录一、编制依据及工程概况·······························31、编制说明·········································32、编制依据·········································3二、工程概况及特点·········································3三、外墙弹性涂料········································31、材料准备··········································32、作业条件······································43、施工方案及技术措施································44、质量要求··········································65、成品、半成品保护措施································76、工程质量控制及检测··································87、质量保证措施······································9四、热固型改性聚苯板外墙外保温系统施工技术方案··················10五、施工总进度计划及保证措施·······························28六、涂料施工工艺、材料系统主要参数指标······················32七、安全文明目标及保证措施··································35第1页共73页编号:时间:2021年x月x日书山有路勤为径,学海无涯苦作舟页码:第1页共73页八、高空作业安全防护措施····································39九、对处理扰民之措施方案····································40十、对防止扰民之措施方案····································41十一、确保工程质量的技术组织措施····························42十二、确保安全生产的技术组织措施····························46十三、保证工程顺利进行的经济措施、合同措施··················50十四、确保文明施工的技术组织措施····················50十五、确保工程工期的保证措施····························52十六、与总包及其他承包人之间的配合协调措施(含监理)···············56十七、成品保护措施··········································59十八、临时用电用水方案······································60十九、其它工程·········································601、安全保证措施·····························602、雨季条件下的施工措施······················60二十、工程质量保修、工期保证及劳务人员保证承诺··············61二十一、本工程的重点及难点······················63第2页共73页编号:时间:2021年x月x日书山有路勤为径,学海无涯苦作舟页码:第2页共73页一、编制说明及编制依据1、编制说明本工程位于楼全部为超高层建筑,临街配套底商,地下为地下车库,其中地上部分37~40层,地下建筑面积约万平方米;地上部分为万平方米,总建筑面积约23.68万平方米。2、编制依据1.1施工图图纸1.2《建筑施工手...