目录一、项目概况....................................................................................................................................................1二、SCR催化剂存放及装卸.............................................................................................................................12。1催化剂模块存放的要求...........................................................................................................................12.1催化剂模块的装卸要求..............................................................................................................................12.3存放库房的要求..........................................................................................................................................12.4催化剂分层堆放要求..................................................................................................................................2三、SCR催化剂的安装.....................................................................................................................................23。1催化剂安装流程.......................................................................................................................................33。2初始催化剂安装的时间...........................................................................................................................33。3催化剂的搬运..........................................................................................................................................33。4SCR反应器内催化剂的安装顺序..........................................................................................................43。5催化剂安装...............................................................................................................................................43。6无轨运载小车的催化剂初始安装...........................................................................................................43。7利用检修葫芦的催化剂初始安装...........................................................................................................53。8催化剂的安装与要求...............................................................................................................................63。9安装过程的一些注意事项.......................................................................................................................7四、安全文明施工............................................................................................................................................74。1安全施工管理..........................................................................................................................................74.2职业健康及环境管理措施.........................................................................................................................8催化剂吊装施工方案一、项目概况项目名称:河北迎新玻璃集团有限公司#4线玻璃窑烟气脱硝除尘项目位置:河北省沙河市迎新玻璃集团有限公司玻璃厂内二、SCR催化剂存放及装卸催化剂存放和装卸需要严格地按照供应商提供的说明和要求实施,使其能达到保证的脱硝效果。2。1催化剂模块存放的要求(1)催化剂应当封装存放,只有当催化剂被安装到SCR反应器时才可拆封。(2)封装好的催化剂应当在室内存放。(3)封装好的催化剂不能倒放。(4)封装好的催化剂不能接触包括雨水、油、酸性物质以及有毒化学物质在内的任...