中铁五局(集团)有限公司黔张常铁路项目经理部目录1编制说明.....................................................11。1编制依据...............................................11。2适用范围...............................................11.3编制原则................................................12工程概况.....................................................22.1工程简介................................................22。2工程地质情况...........................................42。3水文地质特征及评价.....................................42.4气象资料................................................42.5既有构筑物情况..........................................42.6交通条件................................................42。7工程特点...............................................53施工部署与资源配置...........................................43.1总体施工原则............................................43.2现场总平面布置..........................................43.3主要机具及设备配置......................................43。4劳动力配置使用计划.....................................53。5临水临电方案...........................................53.6现场准备................................................54施工方案.....................................................64。1冷却管安装.............................................64。2温控监测设备和测试布置图...............................74。4混凝土浇筑顺序........................................104。5混凝土保温和保湿养护方法..............................104。6特殊气候条件下的施工..................................114。7大体积砼温度裂缝控制主要技术措施......................125施工进度计划................................................145。1承台施工进度计划......................................145。2功效指标..............................................165.3进度保证措施...........................................166工程质量管理................................................186。1质量管理控制体系......................................186。2质量保证措施..........................................18新建黔张常铁路QZCZQ-5标二分部大体积承台混凝土专项施工方案中铁五局(集团)有限公司黔张常铁路项目经理部6.3大体积砼温度裂缝控制主要技术措施.......................187安全生产管理................................................217.1安全目标...............................................217.2安全管理机构...........................................217.3安全保证体系...........................................217.4安全措施...............................................217。5安全文明施工..........................................248施工成本管理................................................258.1成本管理组织机构.......................................258.2成本管理措施...........................................259环水保管理..................................................289。1组织机构..............................................289.2重要环境因素、管理目标.................................289.3环水保措施及环境事故应急预案...........................289.4环水保保证措施.........................................3010文明施工...................................................3110。1文明施工保证体系.....................................3110.2文明施工措施..........................................3111应急预案...................................................3211。1应急机构..................