.目录一、编制依据...........................................................................................................................2二、工程概况...........................................................................................................................2三、项目临建总体部署...........................................................................................................31、项目部选址.....................................................................................................................32、场地平面布置.................................................................................................................33、临建施工总体目标.........................................................................................................44、临建施工资源配置.........................................................................................................55、临建施工方案.................................................................................................................6四、拌合站施工方案...............................................................................................................91、选址原则.........................................................................................................................92、料仓设置.......................................................................................................................103、排水设施布置...............................................................................................................104、场内交通布置...............................................................................................................115、场地建设.......................................................................................................................116、4#站建设方案...............................................................................................................14五、临时便道施工方法.........................................................................................................221、场地清理.......................................................................................................................222、开挖地段.......................................................................................................................223.填方地段.........................................................................................................................23六、质量保证措施.................................................................................................................26七、施工安全措施.................................................................................................................26八、环境保护措施.................................................................................................................27..项目临建方案一、编制依据《中铁一局集团第二工程有限公司施工临建标准》的通知(中铁一二施[2013]37号)《哈佳客专标准化管理的要求》《哈佳铁路7标大临用地的批复》二、工程概况标段起讫里程为DIK275+013.44~DIK327+843.12,线路长度52.83km,位于哈尔滨依兰县及佳木斯市境内,合同工期54个月。合同造价19.64亿元。主要工程包括:双线隧道2座,其中猴石山隧道3410延长米,胜利隧道405延长米;双线特大桥25155.96延长米/14座,双线大桥797.71延长米/3座,双线中桥314.01延长米/3座;涵洞12...