重庆铝业环保搬迁大板锭热电动力车间附属建筑工程厂区围墙施工方案审批:审核:编制:中冶建工集团有限公司2012年9月12日重庆铝业环保搬迁大板锭项目热电动力车间附属厂房建筑工程厂区围墙施工方案目录1、工程概况1
1工程简介·········································31
2施工难点·········································32、施工部署及资源配备计划2
1施工安排·········································32
2资源配备计划·····································42
3施工平面布置·····································43、围墙主体施工3
1土方施工·········································53
2基础施工·········································53
3砌体施工·········································64、工程质量控制及保证措施········································75、安全文明施工措施·········································8中冶建工集团有限公司CHINAMETALLURGICALCONSTRUCTIONCO
,LTD2重庆铝业环保搬迁大板锭项目热电动力车间附属厂房建筑工程厂区围墙施工方案1、工程概况1
1工程简介三标段二期厂区围墙设计为实体围墙,基础必须位于老土之上且地基承载力特征值不小于120Kpa,基础为C20混凝土,地面以下采用M10水泥砂浆砌筑MU10烧结砖,地面以上采用M