清华控股创新基地暨科创慧谷(青岛)孵化器一期工程C、D区编制:审核:批准:中铁十七局集团科创青岛科技园项目经理部二〇一四年十二月目录一、编制依据.........................................................................................................................................................0二、工程概况.........................................................................................................................................................0三、冬季施工现况..................................................................................................................................................1四、方案概述.......................................................................................................................................................21、冬期施工概述:...........................................................................................................................................22、具体工艺组成:...........................................................................................................................................2五、施工前准备....................................................................................................................................................21、材料准备:...................................................................................................................................................32、施工人员的准备:.......................................................................................................................................33、气候条件及时掌握:....................................................................................................................................3六、施工工艺.......................................................................................................................................................3七、冬施保证措施................................................................................................................................................4八、冬季施工安全教育及培训............................................................................................................................5九、现场安全管理................................................................................................................................................5十、成品保护.......................................................................................................................................................6十一、安全生产施工组织设计............................................................................................................................6外墙保温冬季施工方案一、编制依据序号名称标准号(图集)1《建筑节能工程施工质量验收规范》GB50411-20072《外墙外保温工程技术规程》JGJ144-20043《外墙外保温构造详图》L07J1104青岛市城乡建设委员会关于进一步加强建筑外墙外保温工程质量管理的通知青建管字〔2012〕49号5《建筑节能工程施工质量验收规范》GB50411-20076《建筑装饰装修工程质量验收规范》(GB50210-2001)7《建筑装饰装修工程质量验收规范》(GB50210-2001)二、工程概况本工程建设地点位于青岛高新区西至静园路,东至秀园路,北至广博路,南至广盛路交汇处,全地块地下1层为车库及储藏室;地上部分共17栋,其中4层共5栋、5层共10栋、12层1栋、14层1栋。工程类别为二类,设计使用年限为50年,建筑耐火等级为地上二级、地下一...