玉华煤矿后沟风井项目场地竖向布置工程施工组织设计陕西顺泰集团双达建筑有限公司二〇一五年九月二十二日目 录一、编制依据······································1二、工程概况及实施目标····························3三、施工组织 ·····································4四、资源配备计划···································8五、施工技术及施工方法····························9六、施工进度计划及工期保证措施···················24七、质量管理体系及保证措施························27八、季节性施工措施································34九、安全管理体系及保证措施························37十、环境保护体系及措施····························47十一、现场施工总平面布置··························51一、 编制依据1、陕西陕煤铜川矿业有限有限责任公司玉华煤矿后沟风井项目场地竖向布置工程施工招标文件2、公司的技术装备及《质量手册》《程序文件》3、玉华煤矿后沟风井项目场地竖向布置工程施工图纸4、工程应用的主要规程、规范1)《建筑工程文件归档整理规范》GB/T50328-2001
2)《建筑边坡工程技术规范》GB50330-2002
3)《建筑工程施工质量验收统一标准》GB50300-2001
4)《混凝土结构工程施工质量验收规范》GB50204-2002
5)《混凝土结构设计规范》GB50010-2011
6)《建筑工程项目管理规范》GB/T50326-2001
7)《地基与基础工程施