C6排水管道测量成果记录表工程名称龙感湖互通至城区一级公路配套工程二标水准点编号及高程(m)13.493起止桩号K 83+300~K 8 7+7 00记录编号01施工单位湖北永发市政建设有限公司后视读数(m)1.32仪器高(m)1.32测量日期2012.8.17项 目检查井号12241225122612271228122912301231中线位移左偏差(mm)3237293827右偏差(mm)261819井盖高程前视读数(m)1.271.261.251.231.311.291.251.31实测高程(m)13.11713.13513.14613.15413.16313.18913.18613.217设计高程(m)13.1213.1313.1413.1613.1713.1813.1913.21偏差值(mm)-756-6-79-47管内底高程前视读数(m)3.073.063.053.033.023.013.002.98实测高程(m)11.61611.61611.61311.6011.60311.60811.61211.608设计高程(m)11.6211.6211.6111.6111.6111.6111.6011.60偏差值(mm)-4-43-10-7-2128井底高程前视读数(m)3.273.263.253.233.223.213.203.18实测高程(m)11.41611.41611.41311.4011.40311.40811.41211.408设计高程(m)11.4211.4211.4111.4111.4111.4111.4011.40偏差值(mm)-4-43-10-7-2128测量人: 记录人: 校核人: 技术负责人:C6排水管道测量成果记录表工程名称龙感湖互通至城区一级公路配套工程二标水准点编号及高程(m)13.493起止桩号K 83+300~K 8 7+7 00记录编号0 2施工单位湖北永发市政建设有限公司后视读数(m)1.28仪器高(m)1.28测量日期2012.8.17项 目检查井号12321233123412351236123712381239中线位移左偏差(mm)21263123右偏差(mm)35213612井盖高程前视读数(m)1.231.231.201.191.281.251.211.27实测高程(m)13.11713.13513.24613.25413.26313.28913.28613.217设计高程(m)13.2213.2313.2413.2513.2713.2813.2913.30偏差值(mm)-3-756-6-79-43管内底高程前视读数(m)3.073.063.053.033.023.013.002.98实测高程(m)11.61611.61611.61311.6011.60311.60811.61211.608设计高程(m)11.6011.6011.6011.5911.5911.5911.5811.58偏差值(mm)-4-43-10-7-2128井底高程前视读数(m)3.273.263.253.233.223.213.203.18实测高程(m)11.41611.41611.41311.4011.40311.40811.41211.408设计高程(m)11.4011.4011.4011.4011.4011.4011.3911.39偏差值(mm)-4-43-10-7-2128测量人: 记录人: 校核人: 技术负责人:C6排水管道测量成果记录表工程名称龙感湖互通至城区一级公路配套工程二标水准点编号及高程(m)13.493起止桩号K 83+...