电脑桌面
添加小米粒文库到电脑桌面
安装后可以在桌面快捷访问

PMP认证模拟题及答案(中英文双语版)VIP免费

PMP认证模拟题及答案(中英文双语版)_第1页
1/64
PMP认证模拟题及答案(中英文双语版)_第2页
2/64
PMP认证模拟题及答案(中英文双语版)_第3页
3/64
200 道全真模拟题 共200 题,正确1 题,整卷得分1 分,随机得分:0 一. 选择题(本大题共200 小题) 1.In crashing a task, you would focus on: A. As many tasks as possible B. Non-critical tasks C. Accelerating performance of tasks on critical path D. Accelerate performance by minimizing cost 赶工一个任务时,你应该关注: A 尽可能多的任务。 B 非关键任务。 C 加速执行关键路径上的任务。 D 通过成本最低化加速执行任务。 正确答案: C 2.'I cannot test the software until I code the software.' This expression describes which of the following dependencies? A. Discretionary B. Soft C. Preferential D. Mandatory or hard “在对软件编码前我不能进行软件测试。”这句话说明了哪种依赖关系? A 随意的 B 软逻辑关系 C 优先 D 强制或硬逻辑关系 正确答案: D 3.Which of the following formulas provides the most accurate result for computing activity duration? A. AD = Work quantity / Production rate B. AD = Work quantity / Number of resources C. AD = Production rate / Work quantity D. AD = (Production rate)(Work quantity) / Number of resources 以下哪个公式能最准确的计算活动历时? A AD(活动历时)=工作数量/生产率 B AD=工作数量/资源数量 C AD=生产率/工作数量 D AD=生产率 x 工作数量/资源数量 正确答案: A 4.Resource leveling: A. deals with the effective use of resources through the scheduling of the project to B. minimize the resource time. C. typically tends to have no effect on the duration of the activities D. tends to increase the original project completion date E. is parallel working for decreasing the project completion date 资源平衡: A 通过对项目进行进度计划编制,使资源时间最小化,有效的利用资源。 B 通常对活动历时没有影响。 C 可能增加原来的项目工期。 D 为了减少项目工期采用的平行工作法。 正确答案: C 5.Which one of the following is NOT a trade-off decision that must be made i...

1、当您付费下载文档后,您只拥有了使用权限,并不意味着购买了版权,文档只能用于自身使用,不得用于其他商业用途(如 [转卖]进行直接盈利或[编辑后售卖]进行间接盈利)。
2、本站所有内容均由合作方或网友上传,本站不对文档的完整性、权威性及其观点立场正确性做任何保证或承诺!文档内容仅供研究参考,付费前请自行鉴别。
3、如文档内容存在违规,或者侵犯商业秘密、侵犯著作权等,请点击“违规举报”。

碎片内容

PMP认证模拟题及答案(中英文双语版)

确认删除?
VIP
微信客服
  • 扫码咨询
会员Q群
  • 会员专属群点击这里加入QQ群
客服邮箱
回到顶部