In crashing a task, you would focus on: A
As many tasks as possible B
Non-critical tasks C
Accelerating performance of tasks on critical path D
Accelerate performance by minimizing cost 赶工一个任务时,你应该关注: A 尽可能多的任务
B 非关键任务
C 加速执行关键路径上的任务
D 通过成本最低化加速执行任务
正确答案: C 2
'I cannot test the software until I code the software
' This expression describes which of the following dependencies
Discretionary B
Soft C
Preferential D
Mandatory or hard “在对软件编码前我不能进行软件测试
”这句话说明了哪种依赖关系
A 随意的 B 软逻辑关系 C 优先 D 强制或硬逻辑关系 正确答案: D 3
Which of the following formulas provides the most accurate result for computing activity duration
AD = Work quantity / Production rate B
AD = Work quantity / Number of resources C
AD = Production rate /