地面砖、花岗岩铺贴施工方案 Construction Scheme of Floor tile and Granite tile Installation 一、准备工作Preparations 1
弹水平线,确定室内地砖完成面±0
The horizontal line, make sure indoor floor tile finish surface elevation of + /-0
水电管线已安装完毕
Water and electricity line already deployed
二、准备材料 Preparation of materials 1
425水泥及中砂,白水泥
425 cement and medium sand and white cement
800*800*25花岗岩,600*600*25花岗岩,600*600*12地砖
800 * 800 * 25 granite, 600 * 600 * 25 granite, 600 * 600 * 12 floor tile
二、施工方法:construction procedure 1、工艺流程 construction process 材料准备→弹楼地面面层标高控制线→基层处理→弹线找中找方→铺贴基准控制标筋→铺贴面层→铺贴踢脚板→养护与成品保护 Prepare materials→Bomb the ground floor surface elevation control line→Base treatment→Bomb line →Lay up the benchmark control standard screed→lay up surface course→Lay up the baseboard→Maintenance and p