地面砖、花岗岩铺贴施工方案 Construction Scheme of Floor tile and Granite tile Installation 一、准备工作Preparations 1. 弹水平线,确定室内地砖完成面±0.00标高。 The horizontal line, make sure indoor floor tile finish surface elevation of + /-0.00. 2. 水电管线已安装完毕。 Water and electricity line already deployed. 二、准备材料 Preparation of materials 1. 425水泥及中砂,白水泥。 425 cement and medium sand and white cement. 2. 800*800*25花岗岩,600*600*25花岗岩,600*600*12地砖。 800 * 800 * 25 granite, 600 * 600 * 25 granite, 600 * 600 * 12 floor tile. 二、施工方法:construction procedure 1、工艺流程 construction process 材料准备→弹楼地面面层标高控制线→基层处理→弹线找中找方→铺贴基准控制标筋→铺贴面层→铺贴踢脚板→养护与成品保护 Prepare materials→Bomb the ground floor surface elevation control line→Base treatment→Bomb line →Lay up the benchmark control standard screed→lay up surface course→Lay up the baseboard→Maintenance and protection for the final product 2、铺贴顺序:Tile installation order (1)、大面积施工时,应用分段顺序铺贴。 Large area construction, segmented order paving (2)、对于整个楼层,要先铺贴独立房间,再铺贴通道或走廊。 For the entire building, first tile separate rooms, then passgeways or corridors. (3)、对于一般房间采用退步法先由房间中部向两侧铺贴。对于有独立柱的大厅,要先铺贴柱间部分,然后再向两边展开。 For General rooms, use regression method by laying up from the central to both sides. For the great hall with independent column, first tile column section, then expand to both sides. (4)、所有房间先铺贴整块板材,非整块板材最后铺贴。地面铺贴完后再铺贴踢脚板。 All the rooms firstly paved with block plate ,or tile at last. Skirting board tiled after the ground . 3、铺贴方法:Tile installation method (1)、以提前做好的标筋为基准,首排板材两边挂线,首排铺...