下载后可任意编辑工程项目中网络进度计划编制标准化讨论摘要: 由于目前大多数网络进度计划软件仅提供了网络进度计划的计算、分析、优化、控制等功能,而没有提供辅助编制功能。造成不同工程人员编制出的网络计划差异很大,且对编制的网络进度计划的可行性评价较难。探讨了工程项目中网络进度计划编制标准化的内涵,并就 p3(primavera project planner)软件二次开发以及该软件与一个网络计划软件-network 耦合问题进行了讨论,探究了工程网络进度计划编制标准化的一条路径。最后以实际工程的施工进度计划对该耦合系统进行验证。abstract: since most of the current project management software only offer functions of network schedule plan calculation, analysis, optimization, control, and so on, but have not provided the function of auxiliary making. this causes different engineering staffs making different network schedule plans which are also very difficult to evaluate. based on the characteristics of hydraulic engineering, this paper discusses the connotation sense of standardization of making network schedule plan in hydraulic engineering, and studies on the secondary development of p3 software and its coupling with a network schedule plan software-network to explores a making standardized path of hydraulic engineering network schedule plan. finally, this coupling system is verified as feasible through the actual construction schedule.关键词: 施工组织管理;网络进度计划;编制标准化;p3 软件二次开发key words: hydraulic engineering;network schedule plan;making standardization;p3 software secondary development中图分类号:tu723 文献标识码:a 文章编号:1006-4311(2024)11-0071-020 引言网络进度计划技术是目前工程项目时间、进度计划管理的重要手段之一,对于提高工程建设项目管理水平和效率发挥了重要的作用[1-3]。然而由于施工进度计划编制涉及施工方法、施工资源以及施工所在地的自然和社会环境等众多的因素,这些导致编制一个科学合理、可行的施工进度计划的难度,对同一工程,不同的工程师编制出来...