下载后可任意编辑目 录一、施工组织设计编制依据····························1二、工程概况········································2三、施工组织安排的总体思路和预定目标················4四、施工准备及布置··································6五、施工现场总平面布置······························9六、施工工艺流程···································12七、施工方案·······································14八、高压旋喷桩及锚杆施工的有关技术参数·············25九、淤泥、流沙层处理措施····························27十、基坑支护的变形监测与险情应急对策···············29十一、工程进度计划和保证措施······················32十二、施工机具、劳动力配备的保证···················34十三、工程质量保证体系及措施······················36十四、安全生产及保证措施··························42十五、环境保护及文明施工措施······················46附:施工进度计划横道图施工进度计划网络图施工现场平面布置图徽商·国际大厦基坑支护观测平面图一、施工组织设计编制依据1、采纳及执行的法律规范和标准:国家、安徽省、合肥市有关地基基础工程、基坑支护工程的法律规范、规定和标准
下载后可任意编辑2、设计图纸及文件:安徽省岩土设计讨论所设计的《合肥绿地有限公司徽商·国际大厦基坑支护图》
3、安徽省建筑工程勘察院提供的《岩土工程勘察