文件名称耐压测试作业指导书Work instructions for Proof-voltage tests 文件编号WI--031 版本E 生效日期页次1 /51.0 目的 Purpose 规范耐压测试作业规程,确保产品的电气安全性能符合标准要求。Pressure testing norms order to ensure that products meet the electrical safety performance standards. 2.0 范围Scope 适用于本厂电气安装完备之成品灯具的耐压测试。Apply to the factory's products complete the installation of electrical lamp voltage of the test. 3.0 测试仪器 /工具Testing equipments / Tools 耐压测试机Pressure tester 4.0 测试步骤Test Step 4.1 测试前准备Test preparation 4.1.1 测试前先检查各电器部件是否完好,确认 OK 后,打开总电源开关;Before the test, please check whether the electrical equipment parts is good, and then open the switch after be sure is OK. 4.1.2 调整漏电电流旋扭至适当位置(具体见 4.1.7 对照表 );Adjustment current leakage to the appropriate location (see 4.1.6 specific schedule) 4.1.3 设定测试时间 :依待测体之规格要求设定定时器的测试时间(使用定时器必须将定时器开关置于“开 ”的位置);Set test time: according to test specifications body set timer test time (using the timer switches must be placed "on" position) 4.1.4 测试电压的设定:将定时器开关置于“关”的位置 ,并确认“输出 ”指示灯未显示及耐压输出表指针是否归零位,然后按“测试”按钮,顺时针调整耐压输出旋钮至适当位置(具体见 4.1.7 对照表 );Test voltage settings: timer switch will be placed "off" position and confirm that "output" light output voltage and did not show whether the zero-table pointer, and then press the "test" button and adjust the voltage output clockwise Knob to the appropriate location (see 4.1.6 specific schedule) 4.1.5 若在准备状态时已设定好耐压输出值则不需按测试按钮,无输出则不必调整耐压输出按钮。If in the preparation of state has set a good voltage output value is not subject to the test button, without ha...