某度假酒店山体边坡治理方法某度假酒店山体边坡治理方法 摘要:目的:讨论某度假酒店山体边坡治理方法。方法:根据文献资料与多年经验进行归纳总结。结果:土方回填-锚杆工程-土方开挖-锚杆工程-如此反复至基础-挡土墙施工-消防路面施工-格构梁施工。结论:根据本工程实际情况,土方工程必须采纳先回填再分层开挖的方法。锚杆杆体采纳 3C 25HRB400 级钢筋点焊成束,锚头采纳 3C25HRB400 级钢筋与锚杆双面满焊或锚杆杆体钢筋直接弯钩,对中支架采纳 φ12 钢筋与锚杆钢筋点焊连接。边坡采纳钢筋混凝土格构梁+挡土墙+锚杆的支护方式。 关键字:山体;边坡;治理;加固 Abstract: Objective: To discuss the treatment method of a resort hotel mountain slope. Methods: Based on the literature and years of experience summarized. Results: Earthwork backfill - the anchor project - earth excavation - bolt works - and so forth to the foundation - retaining wall - Fire road construction - lattice girder construction. Conclusion: According to the actual situation of the works, earthworks must be used first backfill stratified excavation method. The anchor rod using 3C 25HRB400 grade steel welding beam, anchor head with hook 3C25HRB400 grade steel with full bolt-sided welding or bolt rod reinforced directly φ12 steel and bolt steel spot welding on the bracket. Slope reinforced concrete lattice beam + retaining wall + bolt the support method. Keywords: mountain; slope; governance; reinforcement 中图分类号:U456.2 文献标识码:A 文章编号: 天津蓟县圣光温泉旅游度假酒店工程位于天津市蓟县,总建筑面 59286?,地下一层,地上五层,建筑高度 23.95m,结构类型为框架结构。 施工顺序 土方回填-锚杆工程-土方开挖-锚杆工程-如此反复至基础-挡土墙施工-消防路面施工-格构梁施工。 主要施工内容 一、土方工程 根据本工程实际情况,土方工程必须采纳先回填再分层开挖的方法,具体土方量详见土方方格网图及现场签证。 1.土方回填 山体为一定角度的坡面,要在山体表面施工必须制造施工面。故回填与山体坡面平行,宽度为 5m 的回填土...