序号分项工程工程量计算式单位定额工程量清单工程量1建筑面积(22.1+0.14)×(14+0.14)×6=1886.84㎡1886.842平整场地(22.1+0.14)×(14-0.14)=314.48㎡314.48314.483挖基础土方1.5×2.1×54.89+1×2.1×1.9+1.9×2.1×11.5×2+2.1×2.1×27.275+1.6×2.1×13.5=434.31m³434.31挖沟槽1-1 (1.5+2×0.3+0.5×2.1)×2.1×54.89+1/3×0.5² ×2.1³=363.872-2 (1+2×0.3+0.5×2.1)×2.1×1.9+1/3×0.5²×2.1³=11.3453-3 (1.9+2×0.3+0.5×2.1)×2.1×11.5+1/3×0.5² ×2.1³=86.5044-4 (2.1+2×0.3+0.5×2.1)×2.1×27.275+1/3×0.5 ²×2.1³=215.5625-5 (1.6+2×0.3+0.5×2.1)×2.1×13.5+1/3×0.5² ×2.1³=92.91m³770.19钎探S 槽=1.412×0.3×54.89+1.6×1.9+2.5×11.5+2.7× 27.275+2.2×13.5=158.38㎡158.38余土外运=576.18-490.515-50.981=34.684m³33.994挖基础土方3.1×3.1×2.1×4+2.2×2.2×2.1× 6=141.708 m³141.71挖地坑JC-1 V=[(3.1+2×0.3+0.5×2.1 )²×2.1+1/3×0.5²× 2.1³]×4=192.607JC-2 V=[(2.2+2×0.3+0.5×2.1)²×2.1+1/3×0.5² ×2.1³]×6=31.899m³224.51钎探S 坑=(3.1+2×0.3)²×4+(2.2+2×0.3)²×6=101.8㎡101.85基础回填土V 挖土方=V 地坑+V 沟槽=434.31+141.708=576.18扣除:①独立基础、条形基础、以及基础下的垫层 =25.406+5.259+51.111=81.775 ② 室外地坪-0.3 以下的柱: 4×0.4²×(1.7-0.3)+6×0.4²×(1.7-0.3)+11 × 0.24²×(1.8-0.3)=3.19V 回填=576.18-81.775-3.19=490.515m³490.52V 挖土方=V 地坑+V 沟槽=770.191+224.506=994.697扣除:①独立基础、条形基础、以及基础下的垫层 =25.406+5.259+51.111=81.775 ② 室外地坪-0.3 以下的柱: 4×0.4²×(1.7-0.3)+6×0.4²×(1.7- m³909.73序号分项工程工程量计算式单位定额工程量清单工程量0.3)+11 × 0.24²×(1.8-0.3)=3.19V 回填=994.697-81.775-3.19=909.7326房心回填土h 室内外=0-(-0.3)=0.3 S 净面积=(21.6-0.24)×(13.5-0.24)=283.23V=283.23×(0.3-0.06-0.02-0.02-0.02)=50.981m³50.9850.9877砼垫层 C10砼垫层 C10独立基础垫层:JC-1:V=(1.45×2+0.1×2)²×0.1×4=3.844JC-2:V= (2+0.1×2)²×0.1×6=2.904条形垫层1-1:L=(21.6+0.715×2)×2+(6-0.585-1)×2=54.892-2: L=(2.4-2.9/2)×2=1.93-3:L=(5.1-0.65)×2=11.54-4: L=(5...