水钢隧道下穿铁路既有线施工技术控制水钢隧道下穿铁路既有线施工技术控制 摘要:文章以水钢隧道工程下穿铁路既有线为例,对 D 型便梁布置进行分析计算,结果表明线路加固方案是安全可靠的;大管棚施工、双侧壁导坑法施工中的关键环节提出相应的技术措施,为既有铁路线下隧道施工组织,加强施工技术控制,有效降低施工风险,确保既有线行车安全和隧道施工安全,提供一定的参考
关键词:隧道;铁路既有线加固;大管棚;双侧壁导坑法;施工技术 Abstract:The paper takes SHUIGANG tunnel project for example, according to analysis and calculation of the D-type steel beam plan, the result indicated reinforcement method is reliable
Some suggestions about large-pipe-shed and twin-side heading method of the tunnels beneath the existing railway construction technology are accepted, the measure how to organize construction and strength construction technology control for minimum risk, ensure the safety of tunnel construction and railway lines, provide a certain reference for the relevant workers
Key words:tunnel, railway lines reinf