PMP课堂作业题 四、项目整合管理 - 12 -四、项目整合管理 1 . The project manager has just received a change from the customer that does not affect project time and is easy to complete. What should the project manager do FIRST? A. Make the change happen as soon as possible B. Contact the project sponsor for permission C. Go to the change control board D. Evaluate the other overall impact on the project 1 . 项目经理从客户那里收到了一个变更请求,这个变更并不影响项目时间而且易于完成。这时候项目经理首先应该做什么? A. 尽快执行变更 B. 与项目发起人联系获取许可 C. 去变更控制委员会 D. 评价对项目其他方面的总体影响 2 . Effective project integration usually requires an emphasis on: A. The personal careers of the team members B. Timely updates to the project management plan C. Effective communications at key interface points D. Product control 2 . 有效的项目整合通常需要重点关注 : A. 团队队员的个人职业 B. 及时地更新项目管理计划 C. 在关键的接口处进行有效的沟通 D. 产品控制 3 . A software development project has been suffering through many major project changes. Because of this, the project manager has not been able to do much but complete change control forms. Which statement BEST describes the other activities the project manager should be doing? A. Determine that changes have been made and whether the changes are beneficial.List all of them in the scope management plan B. Determine that a change is beneficial, notify stakeholders affected by changes and determine if the change is needed C. List all changes in the project charter, notify stakeholders affected by changes and ensure the team signs off on all changes D. Notify all stakeholders affected by the change, list all the changes in the scope management plan and determine that...