目 录1 编制依据................................................22 工程概况................................................22.1 工程场地概况.................................................22.2 围护桩分布状况...............................................22.3 参建单位....................................................23 施工准备................................................33.1 破桩头定义...................................................33.2 破桩头的目的.................................................33.3 施工条件.....................................................33.4 机具准备.....................................................33.5 人员安排.....................................................44 施工工艺................................................44.1 工艺流程.....................................................44.2 施工顺序.....................................................44.3 施工注意细节.................................................54.4 破除桩头小技巧...............................................55 质量控制................................................65.2 成品保护.....................................................66 桩头质量缺陷及处理办法..................................66.1 常见桩头缺陷.................................................66.2 缺陷处理措施.................................................67 工期控制................................................78 安全文明施工............................................81 编制依据(1)由公司提供的《***********》基坑围护设计施工图纸;(2)由*****公司提供的《*******岩土工程勘察报告(勘察编号:11020-1)》;(3)相关的各种法律规范规程、法律法规、图集;2 工程概况2.12.1 工程场地概况工程场地概况*********拟建场地位于**西城路和规三路交会处西南角,***东街北侧。下载后可任意编辑场地原地势较低洼,后堆土填积,原有沟塘已填埋整平。场地现为空地,地形略有起伏,地面高程在 5.71~9.60m(吴淞高程系)之间,场地地貌单元属长江漫滩。2.22.2 围护桩分布状况围护桩分布状况本工程基坑总面积约 3...