下载后可任意编辑电 缆 线 路 敷 设 施 工 方 案2012 年 9 月 8 日下载后可任意编辑目录一、 工程概况········································11、电缆设计情况····································12、直埋电缆施工现场情况····························3二、 施工关键工序与作业方法··························31、路径复测和放样··································32、直埋电缆沟开挖··································33、行车道的开挖····································34、电缆的敷设······································4三、 施工质量要求和工艺要点··························4四、 安全技术要求····································6五、 组织措施········································8一、工程概况1、电缆设计情况XXXXXXXXXXX 送电线路工程在 XXXX 炼厂内的进出线是采纳电缆连接架空线路终端塔 G106 和炼厂内升压站的,其敷设方式为直埋式
其电缆设计情况概括如下:一电 缆 主 体电缆名称铝单芯交联聚乙烯绝缘皱纹铝护套阻水电力电缆电缆规格YJLLW03-Z 48/66kV-1×240mm2近似外径(mm)27
8近似重量(kg/km)1060电缆沟深度(m)1电缆沟宽度(m)1
4二电 缆 附 件名称规格单位数量备注166kV 户外电缆头YJZW14-48/68kV套62GIS 户内电