Project Schedule Guarantees 施工进度计划保证措施 1、 MAIN FACTOR AFFECTING THE PROJECT PLAN SCHEDULE 进度计划及影响工期的主要因素 1
1 PROJECT SCHEDULE ACTIVITIES 施工计划编制说明 According to the tender documents, the works required for completion is scheduled to start in November 2011 and complete in April 2012
We will strictly follow the required schedule if we are awarded the project
The total duration including materials purchase, materials' testing, The venue construction and the scope of works listed in the tender documents, all decoration and fitment works
根据招标文件的要求,本工程工期要求为:计划于2011 年11 月开工
我方根据自身情况确定本工程工期目标,并响应招标文件要求
一旦我公司有幸中标将按照招标文件指定日期计划于2011年11 月按时开工,2011 年4 月竣工,严格按照总工期要求安排施工
该时间包括材料采购、材料试验、临时场地建设以及招标文件范围改造装饰装修项目的施工
In order to ensure that the decoration and fitment of project to complete within the