新建铁路厦门至深圳线前场铁路大型货场牵引供电工程施工组织设计编制:复核:审核:中铁十七局集团新建厦门前场铁路大型货场QCSG标项目经理部电气化分部二零一三年九月目录1.编制依据、编制范围及设计概况..........................61.1编制依据...........................................61.2编制范围...........................................61.3设计概况...........................................62、工程概况..............................................62.1工程简况...........................................72.2主要技术标准.......................................72.3主要工程数量.......................................82.4建设项目所在地区特征..............................102.4.1自然特征........................................102.4.2交通运输........................................133施工组织机构...........................................133.1施工组织机构框图..................................133.2项目部主要人员配置................................143.3施工工期安排......................................153.3.1工期安排........................................153.4施工计划横道图及网络图............................154.临时工程和过渡工程....................................164.1施工临时工程和过渡工程用地计划....................164.2临时工程和过渡设置实施方案........................164.2.1施工顺序........................................164.2.2进度安排........................................164.2.3施工方案........................................164.3场地布置及规划原则................................175、施工方案.............................................185.1指导思路..........................................185.2现场调查..........................................185.3接触网工程施工方法................................185.3.1接触网施工工艺流程图............................185.3.2施工测量施工工艺和方法..........................195.3.3接触网基础施工工艺和方法........................225.3.4立杆整正施工工艺及方法.........................255.3.5支柱悬挂装配施工工艺及方法......................275.3.6软横跨安装施工工艺及方法........................295.3.7承力索架设及超拉施工工艺及方法..................315.3.8接触导线架设及超拉施工工艺及方法................335.3.9回流线、架空地线架设施工工艺和方法..............355.3.10附加导线架设与安装施工工艺及方法...............355.3.11接触悬挂架设及调整施工工艺及方法...............375.3.12隔离开关安装与调试施工工艺及方法...............385.3.13分段绝缘器安装施工工艺及方法...................405.3.14避雷器和接地安装施工工艺和方法.................415.3.15接触网冷滑试验和检测...........................416、资源配置方案..........................................446.1劳动力组织........................................446.1.1劳动力组成......................................446.1.2劳动力组织......................................456.1.3劳动力计划......................................456.2主要施工机具......................................456.2.1主要施工机械....................................456.1.2主要施工工具....................................456.1.3主要施工测量仪器................................467、管理措施..............................................467.1安全保证措施......................................467.1.1安全目标........................................467.1.2安全保证体系....................................467.1.3危险源辨识......................................487.1.4安全保证...