银鹭食品集团厦门基地成品仓库改造装货平台工程施工组织设计福建天重钢结构建筑工程有限公司二○一四年二月廿五日目录一、编制说明······················1二、工程概况······················1三、施工部署······················2(一)管理目标······················2(二)施工准备工作程序··················2(三)现场管理机构组织及主要管理人员配备·········2(五)现场管理人员分工岗位责任··············4(六)现场生产准备····················7(七)技术准备······················7(八)施工工艺······················7(九)材料组织及成品、半成品进场计划···········8(十)施工用水、用电···················8四、主要施工方法····················9(一)材料的质量检验··················9(二)钢构件的制作工艺及质量控制·············9(三)钢构件的除锈和涂装················11(四)钢构件的验收出厂·················12(五)钢结构安装····················12(六)铝箔、保温棉、彩钢瓦工程·············13五、工程拟投入主要施工机械进场计划··········15六、劳动力安排计划表·················16七、确保工程质量的技术组织措施············17(一)质量管理工作体系·················17(二)质量目标管理网络·················18(三)施工现场组织···················19(四)现场管理班子尽责分工管理·············20(五)确保分部、分项施工、技术交底质量控制保证措施···21(六)质检制度保证···················23(七)建材质量保证···················25(八)机械设备质量保证·················26(九)施工计划高度管理保证···············26(十)经济政策保证···················26八、确保安全生产的技术组织措施············27(一)安全保证工作体系·················27(二)安全管理制度···················28(三)具体保证措施···················30九、确保文明施工的技术组织措施············31(一)建立现场文明施工管理制度·············31(二)文明施工总体要求·················31(三)落实措施·····················32(四)消防措施方案···················35十、确保工期的技术组织措施··············36(一)项目部协调调度··················36(二)落实技术保证措施·················37(三)夜间施工保障措施·················37(四)防雨施工技术措施·················38十一、施工工期网络图(见附页)·············39十二、施工总平面布置图(见附页)·············一、编制说明1、本施工组织设计依据银鹭食品集团厦门基地成品仓库改造装货平台工程钢结构施工图纸及现行国家、省、市规范、规程、标准、图集、通知,并结合现场条件、工程特点及本公司多年来的施工经验、目前实际的施工技术力量、现行施工组织、施工技术等管理办法、制度进行编制。2本施工组织设计中的工期和质量是结合本公司的现有装备、技术力量、施工经验、施工组织能力综合编制的,并能满足施工招标文件要求。3本施工组织设计做为投标阶段和现场施工指导性文件。各工种工序流水作业及注意事项将在施工合同签定后,班组施工前进行技术交底,做为施工组织设...