浙江正方交通建设有限公司机西高速公路JXZT-1标段排水工程施工方案1目录一、编制依据·············································································2二、工程概况·············································································2三、施工方法和工作程序······························································21
中央分隔带··········································································22
横向排水管施工工艺流程························································33
纵向排水沟施工工艺流程························································74
纵向集水槽施工工艺流程·······················································11四、资源配置计划······································································121、人员安排·········································································122、材料要求······························································