目录××市海关业务技术专用楼.....................................................................................................................3工程概况.................................................................................................................................................3施工准备.................................................................................................................................................42.1 组织准备...........................................................................................................................................42.2 资源准备...........................................................................................................................................42.3 现场准备...........................................................................................................................................82.4 技术准备...........................................................................................................................................9施工进度计划.......................................................................................................................................103.1 工期目标工期为 644 天。.............................................................................................................103.2 总进度计划....................................................................................................................................103.3 月、周计划....................................................................................................................................11施工方案...............................................................................................................................................11施工测量...............................................................................................................................................11模板工程................................