合正尚湾新城一期71、72栋基坑支护工程施工组织设计深圳市地质建设工程公司二О一一年六月九日目录第一章工程概况.........................................101.1工程概况及场地周边环境...............................................................................................1061.2工程地质及水文地质条件...............................................................................................101.3基坑支护方案...................................................................................................................12第二章编制依据及说明...................................132.1编制依据...........................................................................................................................13第三章施工管理机构配置.................................133.1施工现场项目经理部组织管理机构................................................................................133.2项目管理班子配备...........................................................................................................13第四章主要施工机械、设备和劳动力配置...................114.1劳动力计划.......................................................................................................................114.2主要施工机械设备计划....................................................................................................11第五章施工部署及分项施工方案...........................125.1施工总体部署...................................................................................................................125.2分项工程施工方案...........................................................................................................135.2.1施工测量方案...........................................135.2.2微型桩施工.............................................145.2.4土钉墙喷锚支护施工技术措施.............................155.2.5土方开挖...............................................185.2.6排水系统施工...........................................235.3基坑支护监测..................................................................................................................235.3.1沉降、位移观测技术依据.................................235.3.2沉降观测方法...........................................245.3.3位移观测方法...........................................25第六章施工进度控制及工期保证措施.......................266.1目标.................................................................................................................................266.2施工进度计划...................................................................................................................266.3进度控制的方法...............................................................................................................266.4强化进度计划管理...........................................................................................................266.5施工进度的控制...............................................................................................................276.6保证工期的措施...............................................................................................................276.6.1设计变更因素...........................................276.6.2保证资源配置...........................................276.6.3技术因素...............................................286.6.4土方开挖因素......