天然气工程施工组织设计北京市*****公用工程有限公司2008 年 12 月 2 日目 录1、编制依据.............................................................32、工程概况.............................................................33、施工部署.............................................................33.1 项目组织机构.....................................................33.2.施工工期........................................................43.3、施工准备.......................................................43.4.劳动力、主要机械设备、材料计划..................................43.5 工期保证措施.....................................................54、主要施工方法.........................................................54.1、土方工程.......................................................54.2、管道安装及焊接.................................................74.3、阀门安装.......................................................74.4、管道防腐补口...................................................74.5、强压试验.......................................................84.6、严密性试验.....................................................84.7、吹扫...........................................................84.8、调压箱安装.....................................................85、质量目标设计及保证措施...............................................95.1.机构设置........................................................95.2.质量目标........................................................95.3 质量保证措施.....................................................96、安全生产措施.........................................................96.1 机构设置.........................................................96.2 安全管理目标.....................................................96.3 安全防护措施.....................................................97、施工及环境保护管理措施..............................................117.1 文明施工场地目标................................................117.2 场容管理...